It has started!
28th November 2018Exciting times here at Holiday Inn Gatwick Airport as we see the start of our refurbishment! The work is well underway on our top floor bedrooms, they have been completely stripped of the old style Holiday Inn, and the new modern decor is going in as we speak. This is our first phase of the whole project, and come 15th December, we will have one whole brand new floor of bedrooms - 45 of them to be exact.
The second phase will begin right away, with the next floor of 44 bedrooms being stripped and renovated, which we are due to be completed on 9th February.
As you can imagine, the whole team are really excited about the whole process and we cannot wait to see the final product in mid-March, with not only our bedrooms, but our brand new reception, lobby, bar and restaurant as well!
Take a look at our picture gallery to see for yourself and don’t forget to follow the excitement on our Facebook and Twitter too! #HIGatwickGoodtoGreat
We will keep you updated along our exciting journey…stay tuned!